NEC4 practice note 1 gives us a bit more clarity on that and is relevant to NEC3 as well as it is the same point of principle. It was always intended that whilst you use the last Accepted Programme, you take into account progress and other CE's that had occurred up until the point you became aware of the compensation event being assessed.
That being the case, if the Contractor was already in delay by 10 days then the extra over affect due to the CE would only be 10 days not 20. However, if the Contractor can demonstrate that they could have mitigated that delay themselves, then they could still be entitled to the 20 days.
As a general rule you should assess the delays in the order that they occurred.
That being the case, if the Contractor was already in delay by 10 days then the extra over affect due to the CE would only be 10 days not 20. However, if the Contractor can demonstrate that they could have mitigated that delay themselves, then they could still be entitled to the 20 days.
As a general rule you should assess the delays in the order that they occurred.