Employer is to provide access to “section 2” of site on day 20 of programme but this is now delayed by 20 days due to Employer not completing their works.
Contractor is currently working on “section 1” of site which is delayed due to Contractor and all works to “section 1” must be completed before work can start on “section 2”.
When assessing the impact of this CE, the latest accepted programme showed planned completion of “section 1” on day 19 but actual progress on site/next programme submission would show planned completion being on day 30. Should the CE be based on a delay of 20 days due to Employer or does the CE consider the Contractor’s delay and reduce this to only 10 days?
Contractor is currently working on “section 1” of site which is delayed due to Contractor and all works to “section 1” must be completed before work can start on “section 2”.
When assessing the impact of this CE, the latest accepted programme showed planned completion of “section 1” on day 19 but actual progress on site/next programme submission would show planned completion being on day 30. Should the CE be based on a delay of 20 days due to Employer or does the CE consider the Contractor’s delay and reduce this to only 10 days?