Answered: NEC ECC: Does an implemented CE change Completion Date if CE does not impact contract works?

$
0
0
Like any compensation event you assess the impact the CE has had upon planned Completion, and if it has moved it you get to move Completion Date by the same amount. If these additional works have not further moved planned Completion (which is already running late) then there is still NO entitlement to move Completion Date.