A sub-contract agreement was put in place to supply labour and plant to undertake the installation of support steelwork. however the mechanical plant (mastclimber)failed on numerous occasions causing delay and distruption to the Works. The sequence of the programme required other trades to utilise the access equipment to complete thier works
The SOCC is clear that a Defined cost is where the items have been used to Provide the Works, and in this instance when the access equipment has failed, does not meet this criteria. how does the contract deal with the abortive costs incurred by other trades following the delay, and contra charging these to the offending party.
The SOCC is clear that a Defined cost is where the items have been used to Provide the Works, and in this instance when the access equipment has failed, does not meet this criteria. how does the contract deal with the abortive costs incurred by other trades following the delay, and contra charging these to the offending party.