NEC ECC: Can payment be withheld for a time related activity that can never be completed?

$
0
0
The Option A activity schedule had site accommodation costs spread over the contract period as monthly activities. The site establishment was not in place until the second month of the contract. The Project Manager will not pay for this item for the first month of the contract as it was not completed. How does the contract deal with a time related activity like this that can never be completed?