When a Contractor verbally instructs a Subcontractor to de-mob part of work force ( and the Subcontractor issues a CE to coincide with this )

The Contractor then states that they didn't officially instruct the subcontractor in writing to do this therefore are rejecting the CE in question,

How would the Subcontractor reply to above?