NEC ECC: Which accepted programme is used to measure a CE impact?

$
0
0
I have an event occurred where there is extra work which can impact the planned Completion. At the time the event arose we have an Accepted Programme from the previous period. However by the time the instruction was issued by the Employer, we have another Accepted Programme with a new planned Completion. The latter does not include for the impact of the work.

I'm aware that Clause 63.3 denotes the impact on the planned Completion vs the Contract Completion date.

Which programme do we measure the extra work against? The one at the time it arose, or the one at the time of the instruction from the Employer?