Answered: NEC3 ECC: Who's liability is period between "Completion" and "Take-Over"

$
0
0
Between Completion and Take Over the Contractor holds the risk of "Loss of or wear or damage to the works." After Take Over this becomes an Employer's risk-See clause Clause 80.1 Bullet Points 10,11,12,13 for further details.