Answered: NEC ECS: In an Option C subcontract, when is the Pain/Gain assessment made & paid?

$
0
0
The Project Manager makes a preliminary assessment at Completion, which is then included in the next amount due the following period. There is a final assessment made within the final total of the Prices - which will be made at the end of the Defect Date where all the final costs will know be known.