Option C Tendering - received a TQ answer; excl. the Provision of a detailed programme before and during the Contract - I'm under the impression this makes much of Option C irrelevant?
Additionally the client provided an indicative Pricing Schedule, to be filled out and submitted during the tender process, this feels more akin to an Option D contract.
Additionally the client provided an indicative Pricing Schedule, to be filled out and submitted during the tender process, this feels more akin to an Option D contract.