Answered: NEC ECS: Can costs be claimed back under 25.2 for poor performance

$
0
0
No. But what you could do is notify the outstanding works as Defects - a part of the works not in accordance with the Works Information, whereupon they have the defects correction period to correct it. If they fail to do it in this time, then clause 45.1 kicks in (assuming it is NEC3)