Answered: NEC3 ECC: Is the Contractor paid for UK Public Holidays?

$
0
0
The contractor should be paid people costs when he incurs people costs. If that is over a holiday or weekend it doesn't matter. The only caveat to that would be if there were an express term in the contract limiting site times.