Under an ECC3 option C Defined Cost is the cost of the components of the SCC with SCC 13 (a) & (b) allowing the contractor to be entitled to claim for T&S if they are required to provide the works. Furthermore, 52.1 states that the Defined Cost only includes rates and percentages stated in the contract data.

With this in mind am I correct in concluding that T&S claims, i.e. mileage and hotel costs, are subject to overhead and fee percentages as is the case with other costs in the SCC? or am I missing something else in the contract that says otherwise?