If a Contractor notifies via cl. 61.3 of his belief that a cl. 60.1(19) event has occurred, is he required to provide evidence with the notification? Ignore for now the other 3 bullets points of cl. 60.1(19).
The event notified has clearly not stopped the Contractor completing the works (1st bullet of 60.1(19)) so the PM assumes their notification is based on their belief that the event has stopped them completing the works by the date shown on the last Accepted Programme (2nd bullet of 60.1(19)). Surely the claim that the event has stopped the Contractor completing the works by the date shown on the Accepted Programme (AP) can only be demonstrated via submission of a revised programme showing the impact of the event upon the AP.
The event notified has clearly not stopped the Contractor completing the works (1st bullet of 60.1(19)) so the PM assumes their notification is based on their belief that the event has stopped them completing the works by the date shown on the last Accepted Programme (2nd bullet of 60.1(19)). Surely the claim that the event has stopped the Contractor completing the works by the date shown on the Accepted Programme (AP) can only be demonstrated via submission of a revised programme showing the impact of the event upon the AP.