Contract Data on an NEC3 ECSC has been left blank. The main NEC3 ECC applies W1 for dispute resolution.
There is no "flowdown" clause.
W2 not applicable in this jurisdiction.
Does W1 apply by default in the subcontract, or is there in fact no Dispute resolution option adopted?
There is no "flowdown" clause.
W2 not applicable in this jurisdiction.
Does W1 apply by default in the subcontract, or is there in fact no Dispute resolution option adopted?