If under the Subcontract it's a requirement for the Subcontractor to have insurance cover of say £10 million for professional indemnity, but under X18 the Subcontractor’s liability (for either indirect/consequential loss or for Defects found after the defects date) is limited to say £5 million, would this mean that the PI insurance is effective only to £5 million? Or are matters covered under insurances excluded from x18 under the PSS?
↧