NEC ECC - Payment on consumables

$
0
0
The Supervisor on the project is very particular about the type of coffee to be provided in the Site offices. They convince you that an expensive coffee machine should be provided by the Contractor together with an allowance of 300 coffee pods per month to be used in the machine.

What should the Project Manager do to arrange for the Contractor to do this? How would the Contractor be reimbursed for the cost it incurs?