If the Works Information at tender stated that the Contractor was to provide 50 No. 900g cans of spray paint and the Project Manager now requires the Contractor to provide 50 No. 900g cans of Brand X spray paint then that is a change to the Works Information, which is a Compensation Event that changes the Total of the Prices (the target cost) by the difference in defined cost plus Fee.
↧