Answered: NEC ECC - Unapproved Drawing Changes

$
0
0
Your tendered price is deemed to have been based on the provisions of the contract and the Works Information in existence at time of tender. You will need to check the Instructions for Tender and/or Form of Tender or similar to be sure of the actual cut off date eg 1 week before tender submission.

Any changes to the Works Information are, by definition, compensation events that entitle a change to the Prices and Completion Date. The tenderer is not expected to be prescient, if it was it would be doing the lottery not bids!