NEC ECC: Can we claim for delivery of materials on site, if this is not listed as an activity on the activity schedule?

$
0
0
Our NEC3 ECC option A contract has an amendment which states:

The clause states ‘the Price for Work Done to Date is the proportion of the Prices for the proportion of each item in the Activity Schedule that is completed…A proportion of an item in the Activity Schedule that is completed is one which is without Defects which would either delay or be covered by immediately following work’.

Could I claim a proportion of the item, due to delivery of the materials?