By accepting the cl 32 programme the PM is not accepting "new contract Dates". Key dates and Completion Date(s) are adjusted, (mainly, by the compensation event process which is a separate process to programme submission and acceptance.
The PM should not be not accepting on the basis that planned dates have moved beyond the "Contract Dates".
The PM should not be not accepting on the basis that planned dates have moved beyond the "Contract Dates".