Answered: NEC ECC: If the Project Manager accepts a Project programme and the Planned Dates are later than the Contract Dates what is the client accepting?

$
0
0
By accepting the cl 32 programme the PM is not accepting "new contract Dates". Key dates and Completion Date(s) are adjusted, (mainly, by the compensation event process which is a separate process to programme submission and acceptance.

The PM should not be not accepting on the basis that planned dates have moved beyond the "Contract Dates".