Answered: NEC ECS: Option B - Does PWDD include value of unimplemented Compensation Events?

$
0
0
Yes that is correct.

The PWDD relates to work completed in the BoQ.

A compensation event assesses changes to the Prices (63.1)

Assessments for changed Prices are in the form of changes to the BoQ (63.13)

The changes to the Prices (BoQ) are included in the notification implementing a CE (65.4)