The standard termination provisions are set out in Section 9.
From your comments it appears that the Employer has terminated for a reason other than R1 to R21. Was this stated on the termination certificate.
That being the case, and with reference to the standard Termination Table, the amount due is A1 : amount due assessed for normal payments + other items set out in clause 93.1, together with A2: the forecast Defined Cost of removing Equipment, together with A4: the direct fee applied to the excess of the total of the Prices at the Contract Date over the Price for Work Done to Date.
Hope that's clear.
From your comments it appears that the Employer has terminated for a reason other than R1 to R21. Was this stated on the termination certificate.
That being the case, and with reference to the standard Termination Table, the amount due is A1 : amount due assessed for normal payments + other items set out in clause 93.1, together with A2: the forecast Defined Cost of removing Equipment, together with A4: the direct fee applied to the excess of the total of the Prices at the Contract Date over the Price for Work Done to Date.
Hope that's clear.