Answered: NEC ECC: Do I have to credit management charges for cancelled scope due to the Employer terminating the Contract?

$
0
0
The standard termination provisions are set out in Section 9.

From your comments it appears that the Employer has terminated for a reason other than R1 to R21. Was this stated on the termination certificate.

That being the case, and with reference to the standard Termination Table, the amount due is A1 : amount due assessed for normal payments + other items set out in clause 93.1, together with A2: the forecast Defined Cost of removing Equipment, together with A4: the direct fee applied to the excess of the total of the Prices at the Contract Date over the Price for Work Done to Date.

Hope that's clear.