Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Viewing all articles
Browse latest Browse all 3204

NEC ECC: Option C contract - change to Scope

$
0
0
The Contractor has been appointed on an NEC4 ECC Option C contract where the works are design by the Client. The Project Manager instructs the Contractor to stop work on a part of the works because the Client’s designer is considering the implications of a design change. All are keen to avoid any abortive costs if at all possible.

After due consideration, some 2 weeks later, the potential design change is abandoned and the Project Manager immediately instructs the Contractor to proceed with the original design layout, aware there may be a delay and additional costs.

a.    Should the Contractor stop work on the part of the works and what should the Contractor do in order to protect its interests under the contract?
b.    What sanctions are there in the contract if the Contractor does not notify an early warning in a situation where one should have been given?

Viewing all articles
Browse latest Browse all 3204

Trending Articles