Answered: NEC4 ECC: CE quotation preparation

$
0
0
Under NEC3, I would say strictly speaking 'No' as the cost of preparing quotations was specifically excluded from Defined Costs  for options A & B.

Under NEC4, this exclusion has disappeared and I cannot find it elsewhere in the contract.

However, in accordance with clause 63.1, there does have to be a change in Defined Costs, so if the relevant people are salaried and just work a bit longer  to get the quotes out, but aren't paid anything extra, then there is no change in Defined Costs.