NEC ECC: Assessing CE delays against our own delays

A compensation event was notified in May, but due to getting authorisation etc... it will not be started until August. Our last accepted programme was in April.
In that time we have suffered our own delays.
As the CE came first can we impact the last accepted programme at the time of the compensation event increasing our EoT?
Or do we have to use the most current "as-built" information up to the point we'll start the works, and get no EoT?