Answered: NEC3 ECC - Option B - CESMM Filling v Backfilling Payment Working Space

$
0
0
the issue of excavating and backfilling work space is a matter for the Contractor to consider and include within its rates. If it is clear that imported material will be required then that should have been allowed for. I have assume that the Contractor is not seeking a cl 60.1(12) CE.