The percentage for people overheads applies to the Shorter Schedule of Cost Components.
Under the SSCC the People cost is assessed as if the people were employed by the Contractor to determine the Defined Cost. Therefore there are "subcontract people".
The perecentage for people overheads should be applied to the People Cost and if the work was subcontracted work then the subcontracted fee percentage would apply.
Under the SSCC the People cost is assessed as if the people were employed by the Contractor to determine the Defined Cost. Therefore there are "subcontract people".
The perecentage for people overheads should be applied to the People Cost and if the work was subcontracted work then the subcontracted fee percentage would apply.