Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Viewing all articles
Browse latest Browse all 3204

Answered: NEC ECC: Is the Contractor able to refer to a dispute?

$
0
0
Yes, the Contractor can : that is what the dispute procedures are there for !

Do note that implied within clause 60.1 (8) is the ability for the Project Manager to change a decision previously communicated to the Contractor. However, the PM would presumably not change his or her mind unless the Contractor had presented a clear case for why he or she was wrong: I had one where the PM had not turned the page on the Contractor's programme thus giving him only 3 weeks extra rather than 17 weeks when you worked through the full logic.

Perhaps call an early warning meeting discuss.

Viewing all articles
Browse latest Browse all 3204

Trending Articles