Answered: NEC ECC: Sectional completion date for design with no delay damages

$
0
0
The only benefit that I can think of is that it highlights the importance of meeting the date.

However, the drawback is that they categorically canNOT claim any damages for late delivery of design. If they had put it as a constraint in the Works Information (NEC3) or Scope (NEC4), they arguably could, but that is a subject for legal debate !!