Answered: NEC ECC: Accepting the correction of a Defect

$
0
0
I am not sure if there is a 'standard' practice, but NEC3 ECC clause 40.3 (NEC4 41.1) says "The Contractor and the Supervisor each notifies the other of each of his tests and inspections before it starts and afterwards notifies the other of its results."

So, having corrected a Defect and inspected it, even if it is not a prescribed inspection as per the Works Information/Scope, you could notify the Supervisor.

And  if it is a test or inspection to be done by the Supervisor under the contract, they should notify you of their test or inspection results once you have corrected it.