Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Viewing all articles
Browse latest Browse all 3204

Answered: NEC TSC: Non-Standard Price List Items

$
0
0
Option X19 of the NEC3 TSC merely requires the Service Manager to consult the Contractor about the contents of a Task Order before it is issued (clause X19.2), once it is issued it is an instruction to carry out a Task (clause X19.1(2)) which the Contractor has a duty to obey (clause 27.3).

Note the use of the word "consult" not "agree" here, which implies that the Service Manager and Contractor may disagree about the contents of the Task Order however the Service Manager still has the right to issue it.

In terms of how the Prices for the Task are calculated, rates and lump sums from the Price List should be used or Defined Cost plus Fee (clause X19.3 and clause 63.2). Unlike the ECC, rates and lump sums from another source cannot be used in any circumstance.

NEC4 TSC has put more structure around the process for issuing a Task Order which resembles the process for quoting and assessing a compensation event.

Viewing all articles
Browse latest Browse all 3204

Trending Articles