How does the Employer claim for consequential loss and damage to property under Clause X18 NEC3.

1. Our thoughts are
- via, PM notification, PMA & CE or
- claim direct from certificate, like Delay Damages

2. It seems unfair on the Contractor to deduct a potentially large sum from the certificate with no prior formal procedure.

3. How is VAT dealt with on a deduction?