Answered: NEC3 ECS: Option A termination

$
0
0
The place to look is section 9 of the subcontract, with reasons R16, R19 and R20 POTENTIALLY being reasons.

However, I cannot stress enough that you need to be very sure of your reasons for terminating and then follow the contract precisely as, otherwise, rather than being paid for work done plus your fee percentage applied to the remainder of Price minus PWDD, you may end up having to pay the Contractor the costs of getting someone else in to complete the subcontracts works.