Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Viewing all articles
Browse latest Browse all 3204

Answered: NEC ECC: Delay costs and acceptance of defects

$
0
0
First of all, it is not the Employer who does this: it is the Project Manager who, in this instance, would be acting as an impartial administrator as per Costain v Bechtel.

For your question 1: A forecast quote should include for risks that are the Contractor's risk under the contract i.e. up to the point at which they become CEs. So you should allow for weather risks up to the point at which they become a compensation event. If this threshold is subsequently passed, then it is an additional compensation event. If the Employer has deleted the weather risk, you are entitled to allow more for that increased risk.

For your question 2: this seems illogical : if all the Defects have been corrected, why /how does it work to change the Works Info so that work which what is not a Defect now can be done to a reduced standard. I would respond with an early warning pointing out the illogicality of it !

Viewing all articles
Browse latest Browse all 3204

Trending Articles