Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Viewing all articles
Browse latest Browse all 3204

Answered: NEC ECS: Quotation for acceptance of Defect

$
0
0
I agree with Glenn's answer as a sensible commercial way forward. However, contractually, the Project Manager could agree to a reduction in the Prices which varies from a slap on the wrists to an amount which is almost as much as it would cost to take out & replace - ultimately it is at his/her discretion - or as Glenn point out, not at all.