Answered: NEC ECC: Accepted defects

$
0
0
No, it cannot be.

Clause 14.1 of both NEC3 and NEC4 clearly states that acceptance of a communication from the Contractor by the Project Manager or Supervisor does not change the Contractor's liability under the contract.