Answered: NEC ECC: Timing for acceptance of defects 44.1

$
0
0
Yes you would just need to give an instruction to change the Works Information to reflect what they have actually achieved, so that it is no longer a defect.

Don't forget under clause 44 you could have teased out a quotation for a saving in order to accept the defect in the first place, as otherwise why should you accept a lesser standard and they get the financial benefit?