Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Viewing all articles
Browse latest Browse all 3204

NEC3 ECC: Can the Contractor submit a revised Programme without terminal float?

$
0
0
We are currently engaged in in ECC Option D Contract. Contractor's latest accepted Programme was with terminal float of 31 days. Then defects to Permanent works was observed which consequently delays the Contractor. The Project Manager instructs the Contractor to submit a revised Programme and the Contractor submits the revised Programme but the 31 days terminal float was gone. Can the project Manager not accept the said submitted revised Programme and instruct the Contractor to submit a revised Programme maintaining the 31 days terminal float?

Viewing all articles
Browse latest Browse all 3204

Trending Articles