If as a Project Manager I do not agree with a payment application of £100k from Contractor but certify my assessment as £80k. That is then what I expect the Contractor to be invoicing. Do I have to issue a payless notice in this situation, or are payless notices only a legal requirement when I am unable to pay the amount I previously certified.
↧