Under an NEC3 standard Option A contract can new multiple access dates be introduced midway through the contract ? There was initially one access date for the site and there is now a proposal to split parts of the site into different areas, and instruct new access dates to these areas. Could this be done under 60.1(1) PMI ? (how do you amend the contract data part 1). Is this a change to the works information if access dates were not in the original works information ?
↧