As you are not in contract with the other Subcontractor, the answer is 'No' from the other Subcontractor.
However, you may have some recourse from the main Contractor if they did not provide something to you by the time stated in the Contract Data, namely access dates, which would be a compensation event.
There is a however to the however though and that is you might now be time-barred from notifying the compensation event if it is more than seven weeks since it happened.
However, you may have some recourse from the main Contractor if they did not provide something to you by the time stated in the Contract Data, namely access dates, which would be a compensation event.
There is a however to the however though and that is you might now be time-barred from notifying the compensation event if it is more than seven weeks since it happened.