This is an ambiguity created by the Contractor so this would be an instruction to change the Works Information that would NOT be a compensation event and hence Contractor risk. By accepting the design, they are not taking on liability of the submission not complying with the original Works Information. In reality under option C - this would not be a disallowed cost, so the Parties would share the cost of this error (but the target will not change).
↧