NEC ECC: Option A: Instruction 11.2(19)

$
0
0
We, the Contractor, have received a list of equipment from the Project Manager through an email (extract below). The list was not part of the Works Information and we understand this list to be a Change to the Works information (additional works).

"Please find attached the equipment list. Please also find attached Early Warning regarding the list."

We need clarity if the above text constitutes an instruction under Clause 11.2(19) and if this should be instructed via a Compensation Event under Clause 60.1(1)?

Note: All parties were aware of the list and works required (although we believe this should be confirmed in the instruction to ensure its existence under the Contract).