Answered: NEC ECC: Can I ask to see the Subcontractor rates when assessing a CE?

$
0
0
Well, you can ask, but whether the Contractor needs to show depends:

Under NEC3 ECC, options A & B, the answer is 'No' as the Contractor is paid according to the Shorter Schedule of Cost Components regardless of whether they are subcontracting or not.

Under NEC3 ECC, options C to F, a Defined Cost is what the Contractor pays to their Subcontractors in accordance with their subcontracts so 'Yes'.

Under NEC4, all options, subcontractor costs have been moved to within the (Short) Schedule of Cost Components and are reimbursed at cost, so 'Yes'.