You’re absolutely correct in your understanding and the Project Manager is correct in their interpretation of the contract. This is not a CE under the contract.
You really should have checked the revised Works Information for changes before signing the contract as this clearly could have affected your price and programme.
You really should have checked the revised Works Information for changes before signing the contract as this clearly could have affected your price and programme.