In accordance with clause 14.3 the Project Manager can give an instruction which changes the Scope (Works Information). Changes to the Scope is generally regarded to exclude the introduction of new items of work not directly associated with the original Scope eg if the original Scope was for Heating and Ventilation then an instruction to install Lifts would not be valid under cl 14.3 and anew contract would be required.
↧