Answered: NEC ECS: Can you have a CE under 60.1(2) after access has first been provided?

By the strict words of the contract, they might be correct. However, there are almost certainly other compensation events headings you can notify under. For example:
60.1 (3) as they are not providing 'something' by the dates on your Accepted Programme (if access is shown as a bar, then each day)
60.1(5) in which all three bullets could apply, but especially the last
60.1(8) a changed decision: they said they would give access, they physically are not.

Further you would not be time-barred as you have "notified a compensation event" - albeit perhaps under the wrong heading - "within 7 weeks" of becoming aware that the event has happened".