Answered: NEC ECC: Is equipment a potential disallowed cost ?

$
0
0
The term 'resources' is not defined and could include Equipment.  Interestingly this bullet point could also include Plant and Materials as the caveat in the previous bullet point is different and relates to different circumstances.