Answered: NEC ECC: Can Contractor claim cost if delayed in correcting a defect that they caused?

$
0
0
If:
- you had put this in your programme which had been accepted then it could potentially be a compensation event under 60.1 (2), (3) or (5) or
- there are provisions in the Works Information / Scope regarding correcting Defects which you followed or give you certain rights which were broken, then it could be a compensation event under 60.1 (5) or
- if it results from an instruction to stop or not start work 60.1(4) or
- the Project Manager changes a decision previously communicated to you 60.1(8).

So 'Yes'!